Skip to main content

Gensco Everett Forklift Charger Relocation

Professional electrical project completed in Everett with precision and quality workmanship.

Project Overview

CK Electric was contracted to complete a full forklift charger relocation and power upgrade at Gensco’s Everett facility. This project required careful coordination and precise installation to ensure uninterrupted warehouse operations.

Our team installed a new 277/480V electrical panel, a 30KVA transformer, and a new 120/208V panel to properly distribute power across the charging stations. We also installed two 120/208V 30A twist-lock receptacles and one 277/480V 20A twist-lock receptacle to support forklift charging needs.

All installations were completed in compliance with commercial electrical codes and with safety as the top priority. The project was delivered on schedule in just three days, minimizing downtime and ensuring the facility was fully operational as quickly as possible.